We can show you a West Covina build rather than describe one. A 1,200 square foot detached ADU, documented stage by stage, with the city inspection dates printed.
Building an ADU in West Covina, in short
Poly Construction Holdings LLC is a licensed California General Building contractor (#1137539) working across the San Gabriel Valley from an office in Rosemead. In West Covina we built a 1,200 square foot detached ADU, 3 bed and 4 bath, permitted by the City of West Covina on 23 July 2026 and carried through to rough-in with every inspection recorded. Structural shell complete starts at $150 per square foot of floor area and takes 50 business days once permits are issued. Interior finishes are contracted separately by the owner.
- Documented project
- Detached ADU, 1,200 sq ft, 3 bed / 4 bath
- Permit issued
- 23 July 2026, City of West Covina
- Licence
- California General Building #1137539
- Shell price
- From $150 per square foot of floor area
- Shell timeline
- 50 business days, weekends and public holidays not counted
- Languages
- Mandarin, Cantonese and English
The inspections, with dates
Most contractors tell you they pass inspections. These are the ones this West Covina project actually passed, in order. They come from the job records, not from memory.
| 1 August 2026 | Footing |
|---|---|
| 18 August 2026 | Under-floor plumbing |
| 18 August 2026 | Gas piping test |
| 26 August 2026 | Under-floor framing and insulation |
| 27 August 2026 | First floor diaphragm |
| 9 September 2026 | Framing and roof diaphragm |
| 17 September 2026 | Rough electrical and mechanical |
| 17 September 2026 | Exterior lath |
| 17 September 2026 | Exterior weather barrier |
What the structural shell price covers in West Covina
| Item | In the structural shell | Contracted separately by the owner |
|---|---|---|
| Time to structural shell complete | 50 business days, weekends and public holidays not counted | Finishing runs after shell sign-off |
| Foundation | Included | Not applicable |
| Structural framing | Included | Not applicable |
| Roof | Included | Not applicable |
| Exterior walls | Included | Not applicable |
| Windows and exterior doors | Included | Interior doors and trim |
| Plumbing, electrical and HVAC | Rough-in only | Finish fixtures, lighting and appliances |
| Flooring, cabinets and countertops | Not included | Owner contracts separately |
| Interior paint | Not included | Owner contracts separately |
Design, construction drawings and West Covina permitting are handled by us as part of the project and are quoted separately from the per square foot shell price. You receive a written, itemised scope before signing anything.
West Covina ADU questions
Have you actually built in West Covina?
Yes, and the whole job is published. A 1,200 square foot detached ADU, 3 bed and 4 bath, permitted by the City of West Covina on 23 July 2026. Three Site Journal posts follow it from rebar through to rough-in, with photographs and the dates each inspection passed.
Who handles the West Covina permits?
We do. Construction drawings, submission, plan check corrections, the permit itself, and then the inspections through to sign-off. On the documented project the permit was issued on 23 July 2026.
What does an ADU cost in West Covina?
Structural shell complete starts at $150 per square foot of floor area. That covers the foundation, framing, roof, exterior walls, windows and exterior doors, and the plumbing, electrical and HVAC rough-in. Interior finishes are contracted separately by the owner. Final cost depends on size and site conditions, so we will not quote before seeing the property.
How long does it take?
50 business days to structural shell completion once permits are issued, with weekends and public holidays not counted. Design and city permitting come before that, and interior finishing after.
Can I build an ADU on my West Covina lot?
Usually yes, but what you can build depends on your particular parcel rather than a rule we can quote in advance. We look at the lot, check it against the current requirements, and tell you plainly what it will support. That evaluation is free.
Can we do all of this in Chinese?
Yes. Mandarin, Cantonese and English, from the first site visit through drawings, contract, permit questions and the final walkthrough.
Find out what your West Covina lot allows
Free evaluation, no obligation. Tell us the address and we will tell you what it can hold.