Inside the wall: drain stacks and steel protection plates
Drain stacks run up between the studs, copper supply lines are stubbed out at each fixture location, and electrical cable crosses the studs horizontally. The detail worth looking at is every point where a line passes through a timber member: a steel plate is nailed to the face of it. That spot will be hidden behind drywall, and when the owner later hangs a mirror, fits a shelf, or nails in skirting, a screw can land right on the line. The plate is what stops it. The gaps around each penetration are sealed as well.
HVAC and electrical: lines bundled up into the roof structure

The white jacketed runs are the HVAC refrigerant line set, printed with the two line sizes, 3/8 inch and 3/4 inch. They are bundled with the condensate line and the control cable and taken up the wall into the vaulted ceiling. Where the bundle crosses a brace, two steel plates hold the face of the timber. Once this run is closed into the ceiling, reaching it again means taking the ceiling back off.
Bathroom: rough-in set out, and daylight

The bathroom drain lines are set out along the wall at the heights the fixtures will sit. The window is installed with the factory labels still on the glass, and the round ceiling box is fixed. This ADU is planned as 3 bed, 4 bath, and every room's lines are set out to the drawings one by one.
Outside: lath and windows, signed off the same day

On the same day, 17 September 2026, the rough electrical and HVAC inside and the exterior lath outside all passed inspection together. The wall is currently weather barrier plus lath, with the windows installed and flashed, and the stucco has not started. This is the last milestone before the stucco coats go on.
A note on timing: this post documents the rough-in stage of September 2026. The Insulation and Drywall lines on the inspection card are both still blank, so neither has been signed off yet, and the exterior stucco has not started. We don't announce a completion date ahead of time: every milestone is tied to an actual city inspection record, and we'll keep updating the Site Journal with current photos. Two earlier posts cover this project: the foundation stage and the overall progress.
FAQ
Questions people ask about the rough-in stage
What actually happens during the rough-in stage of an ADU?
Rough-in is where everything that will be hidden inside the walls and ceiling gets installed in one pass, before drywall goes up: drain and water supply lines, electrical cable and device boxes, and the refrigerant and condensate lines for the HVAC system. The city inspects and signs off on this work before the walls are allowed to be closed. Poly Construction's structural shell price, from $150 per square foot of floor area, includes the plumbing, electrical and HVAC rough-in. Interior finishes (flooring, cabinets, paint and fixtures) are contracted separately by the owner.
Why are steel plates fitted where pipes pass through the framing?
Where a pipe or cable passes through a stud or a brace, that spot ends up hidden behind drywall. Later the owner hangs a mirror, puts up a shelf, or nails in skirting, and a screw can land exactly on that line. A nail through a water line means a leak; a nail through a cable is worse. A steel protection plate fixed to the face of the timber blocks that spot so the fastener cannot reach the line. It is required by the California building code and is one of the things the inspector checks run by run.
Which city inspections has this West Covina ADU rough-in passed?
Per the City of West Covina building inspection record: Framing passed 9 September 2026, Rough Electrical and Mechanical (HVAC) both passed 17 September 2026, the Gas Piping Test passed 18 August 2026, and Exterior Lath passed 17 September 2026. The permit was issued on 23 July 2026 under permit numbers B24-1438, E24-0942, M24-0426 and P24-0544.
When do insulation and drywall happen, and where is this project now?
As of this post, the Insulation and Drywall lines on the inspection card are both still blank, so neither has been signed off yet; they are the next steps. Outside, the wall is finished to lath and the stucco has not started. We don't announce a completion date ahead of time; every milestone is tied to an actual city inspection signature.