Site Journal · · Poly Construction Site Team · Last updated October 8, 2026

West Covina ADU Rough-In: Water, Power and HVAC Before the Walls Close

Key facts

Project
Detached ADU, 1,200 sq ft, 3 bed / 4 bath
Location
West Covina, California (San Gabriel Valley)
Builder
Poly Construction Holdings, CA General Building licence #1137539
Stage in this post
Rough-in: plumbing, electrical and HVAC, before drywall
Inspections passed
Framing 9 Sept, Rough Electrical and Mechanical 17 Sept, Exterior Lath 17 Sept
Price basis
Structural shell complete from $150 per square foot of floor area
Included in that price
Foundation, framing, roof, exterior walls, windows and doors, and plumbing, electrical and HVAC rough-in
Not included
Interior finishes (flooring, cabinets, paint, fixtures) contracted separately by the owner
Shell timeline
50 business days to structural shell completion, weekends and public holidays not counted
Languages
Mandarin, Cantonese and English throughout the project

Once the drywall is on, you never see inside the walls again. These photos show our West Covina 1,200 sq ft detached ADU (3 bed / 4 bath) at exactly that point: drain stacks, copper supply stub-outs, HVAC refrigerant lines, cable and device boxes all still open, waiting for the city to sign off run by run. Real job-site photos, not renderings.

Interior of the West Covina ADU showing vaulted ceiling framing, partition walls, cable and device boxes in place before drywall
Drain stacks and copper water supply stub-outs in the wall cavity, with steel protection plates where lines cross the framing

Inside the wall: drain stacks and steel protection plates

Drain stacks run up between the studs, copper supply lines are stubbed out at each fixture location, and electrical cable crosses the studs horizontally. The detail worth looking at is every point where a line passes through a timber member: a steel plate is nailed to the face of it. That spot will be hidden behind drywall, and when the owner later hangs a mirror, fits a shelf, or nails in skirting, a screw can land right on the line. The plate is what stops it. The gaps around each penetration are sealed as well.

HVAC and electrical: lines bundled up into the roof structure

Insulated HVAC refrigerant line set and condensate line bundled up the wall into the vaulted ceiling, protected by steel plates at the framing crossing

The white jacketed runs are the HVAC refrigerant line set, printed with the two line sizes, 3/8 inch and 3/4 inch. They are bundled with the condensate line and the control cable and taken up the wall into the vaulted ceiling. Where the bundle crosses a brace, two steel plates hold the face of the timber. Once this run is closed into the ceiling, reaching it again means taking the ceiling back off.

Bathroom: rough-in set out, and daylight

Bathroom rough-in at the West Covina ADU with drain lines set out along the wall, window installed and ceiling box fixed

The bathroom drain lines are set out along the wall at the heights the fixtures will sit. The window is installed with the factory labels still on the glass, and the round ceiling box is fixed. This ADU is planned as 3 bed, 4 bath, and every room's lines are set out to the drawings one by one.

Outside: lath and windows, signed off the same day

West Covina ADU elevation with weather barrier and stucco lath installed, windows and door opening in place, stucco not yet applied

On the same day, 17 September 2026, the rough electrical and HVAC inside and the exterior lath outside all passed inspection together. The wall is currently weather barrier plus lath, with the windows installed and flashed, and the stucco has not started. This is the last milestone before the stucco coats go on.

A note on timing: this post documents the rough-in stage of September 2026. The Insulation and Drywall lines on the inspection card are both still blank, so neither has been signed off yet, and the exterior stucco has not started. We don't announce a completion date ahead of time: every milestone is tied to an actual city inspection record, and we'll keep updating the Site Journal with current photos. Two earlier posts cover this project: the foundation stage and the overall progress.

FAQ

Questions people ask about the rough-in stage

What actually happens during the rough-in stage of an ADU?

Rough-in is where everything that will be hidden inside the walls and ceiling gets installed in one pass, before drywall goes up: drain and water supply lines, electrical cable and device boxes, and the refrigerant and condensate lines for the HVAC system. The city inspects and signs off on this work before the walls are allowed to be closed. Poly Construction's structural shell price, from $150 per square foot of floor area, includes the plumbing, electrical and HVAC rough-in. Interior finishes (flooring, cabinets, paint and fixtures) are contracted separately by the owner.

Why are steel plates fitted where pipes pass through the framing?

Where a pipe or cable passes through a stud or a brace, that spot ends up hidden behind drywall. Later the owner hangs a mirror, puts up a shelf, or nails in skirting, and a screw can land exactly on that line. A nail through a water line means a leak; a nail through a cable is worse. A steel protection plate fixed to the face of the timber blocks that spot so the fastener cannot reach the line. It is required by the California building code and is one of the things the inspector checks run by run.

Which city inspections has this West Covina ADU rough-in passed?

Per the City of West Covina building inspection record: Framing passed 9 September 2026, Rough Electrical and Mechanical (HVAC) both passed 17 September 2026, the Gas Piping Test passed 18 August 2026, and Exterior Lath passed 17 September 2026. The permit was issued on 23 July 2026 under permit numbers B24-1438, E24-0942, M24-0426 and P24-0544.

When do insulation and drywall happen, and where is this project now?

As of this post, the Insulation and Drywall lines on the inspection card are both still blank, so neither has been signed off yet; they are the next steps. Outside, the wall is finished to lath and the stucco has not started. We don't announce a completion date ahead of time; every milestone is tied to an actual city inspection signature.

Wondering if your backyard could fit something like this?

Structural shell complete starts at $150 per square foot, with 50 business days to structural shell completion: foundation, framing, roof, exterior walls, windows and doors, and the plumbing, electrical and HVAC rough-in. Interior finishes are contracted separately by the owner. We'll evaluate your property for free and tell you honestly what's feasible and how long it actually takes in your city.