Site Journal · · Poly Construction Site Team · Last updated September 28, 2026

West Covina ADU Progress: Foundation to Weather Barrier

Key facts

Project
Detached ADU, 1,200 sq ft, 3 bed / 4 bath
Location
West Covina, California (San Gabriel Valley)
Builder
Poly Construction Holdings, CA General Building licence #1137539
Permit issued
23 July 2026, City of West Covina
Price basis
Structural shell complete from $150 per square foot of floor area
Included in that price
Foundation, framing, roof, exterior walls, windows and doors, and plumbing, electrical and HVAC rough-in
Not included
Interior finishes (flooring, cabinets, paint, fixtures) contracted separately by the owner
Shell timeline
50 business days to structural shell completion, weekends and public holidays not counted
Languages
Mandarin, Cantonese and English throughout the project

A 1,200 sq ft detached ADU in West Covina, 3 bed / 4 bath, built by Poly Construction. Permit issued July 23, framing and roof diaphragm passed inspection September 9, and the exterior weather barrier (lath) passed inspection September 17. Here's what's actually on site: not a rendering.

Site walkthrough of this ADU: roof framing, rough electrical and plumbing, windows in, and the exterior weather barrier. Real job-site footage, not a rendering.

Framing: vaulted ceiling structure

The main living space uses a vaulted ceiling frame, with rough electrical boxes and wiring already run at the framing stage, setting up the drywall and electrical finish work that follows.

Exterior: weather barrier and windows

Exterior of the West Covina ADU with lath, windows, and sliding door installed
Close-up of exterior weather barrier lath and window installation

The exterior weather-resistant barrier (lath) is installed and passed city inspection on September 17. Windows and the sliding glass door are in place; stucco is next.

Interior: rough electrical and plumbing

Rough plumbing drain lines installed inside a framed bathroom wall

Rough drain plumbing for the bathroom area is installed inside the framed wall and has passed inspection, consistent with the 3-bed, 4-bath layout.

A note on timing: this project is currently at the framing, rough electrical/plumbing, and exterior weather-barrier stage, it is not finished yet. We don't announce a completion date ahead of time; every milestone here is tied to an actual city inspection record, and we'll update this page with final photos once it's done.

FAQ

Questions people ask about this project

How much does it cost to build an ADU in the San Gabriel Valley?

Poly Construction builds the structural shell from $150 per square foot of floor area. That covers the foundation, framing, roof, exterior walls, windows and doors, and the plumbing, electrical and HVAC rough-in. Interior finishes (flooring, cabinets, paint and fixtures) are contracted separately by the owner and are not included in that figure. Final cost depends on the size of the unit and the conditions on your lot, so a written, itemised scope is issued before anything is signed.

How long does it take to build an ADU in West Covina?

Structural shell completion takes 50 business days. Business days, so weekends and public holidays are not counted. Design and city permitting happen before that and vary between San Gabriel Valley cities, and interior finishing is contracted separately by the owner afterward. On this West Covina project the permit was issued on 23 July 2026, the footing passed on 1 August, framing and roof diaphragm passed on 9 September, and the exterior weather barrier passed on 17 September 2026.

Who builds ADUs in the San Gabriel Valley with Chinese-speaking service?

Poly Construction Holdings (萬盛建設) is a licensed California general building contractor based in Rosemead, serving West Covina, San Gabriel, Alhambra, Monterey Park, Arcadia, Temple City, El Monte, San Marino and Rowland Heights. Mandarin, Cantonese and English are spoken through the whole project, from the first call to the final walkthrough. Licence #1137539 is active and can be verified on the California CSLB website; the company carries $2,000,000 liability cover and a $25,000 bond.

What city inspection milestones does an ADU in West Covina go through?

A detached ADU typically passes through site/grading, footing & foundation, concrete slab, rough electrical/plumbing/mechanical, exterior weather barrier, service panel, and final building inspection, each one inspected on-site and logged in an official city record.

Is Poly Construction licensed and insured?

Yes. Poly Construction holds active California General Building License #1137539, $2,000,000 in liability insurance, and a $25,000 contractor bond, verifiable on the state license lookup. How to verify →

When will this West Covina ADU be finished?

As of September 2026, framing, rough electrical/plumbing, and the exterior weather barrier are complete, it's not finished yet. We don't announce a completion date ahead of time; every milestone is tied to an actual inspection record.

How do I find out if my backyard can fit an ADU?

Book a free property evaluation. We'll visit, review your lot, and explain in Mandarin, Cantonese, or English what's feasible in your city, roughly what it costs, and how long it takes. Book an evaluation →

Wondering if your backyard could fit something like this?

Structural shell complete starts at $150 per square foot, with 50 business days to structural shell completion: foundation, framing, roof, exterior walls, windows and doors, and the plumbing, electrical and HVAC rough-in. Interior finishes are contracted separately by the owner. We'll evaluate your property for free and tell you honestly what's feasible and how long it actually takes in your city.

← Back to Site Journal